On the other hand, the ground floor is almost ready for skimming and we have already bought the first consignment of the rhinoset that is used to smoothen the interior walls before painting. In a few weeks, the following material will be required on the site :
* Ceiling boards (for the first floor only).
* Glass bricks (for the walls on the stair case).
* Window panes.
We will however first compare the prices between Zimbabwe and Botswana as many items are now being accessible locally and cheaper than outside since companies are now starting again although there are still some items that are still costing way too much.
The situation was like this; when the situation was bad here, many companies were producing only for export to our neighbouring countries and their products were not available locally as they wanted foreign currency but now the situation is improving.
The quotation for the Administration block is not yet ready and we are still waiting for the contractor.
* the ground floor can be seen with all the window frames in place.
* the inside partitions on the first floor are complete.
* the workers are plastering all the partitions onthe first floor.
* all the windows and door frames on the first floor are in place and the corridor is done.