giovedì 21 maggio 2009

Weekly Update

The construction of the classroom block is going on and to date the following has been done :

* the roof trusses are almost ready as they are now making them level.
* skimming of the ground floor has since been completed
* painting of the ground floor has since commenced
* we bought all the paint for the buiding.

What is needed in the next few weeks:

* Window panes.
* Doors, door handles and locks.
* Material for ceiling.
* Floor and wall tiles.
* Electrical fittings, lights, switches and plug sockets.

Nessun commento: