lunedì 16 marzo 2009

March 2009_Updates

This week has been quite a busy one, with all the workers doing two shifts as some were wroking during the day and and some during the night busy pouring the concrete and they have since finished more than half of the first floor deck.

They will now wait for fifteen days before they remove the shatter boards on the finished part but as from today they will continue to go up with the other columns that are on the side where the deck is ready.

We now have the quotation for the roof trusses ready and we should make the payment and they should be ready after a week. The next thing will be the roof tiles we are still comparing the best bet between buying them from South Africa and locally.

Due to power cuts, we managed to secure a three phase generator for back up and it so happened that on the very same day they started to pour concrete, we experienced a power cut and fortunately we had the generator from friend and we had no interuptions.

All the window frames and door frames for the main entrance to the classroom block were delivered to the site yesterday.

In summary, we are working according to the schedule and plan.